Sometimes true strength lies in the details – and in speed. Recently, we had the opportunity to impressively demonstrate to a client how quickly and smoothly an INOSTA chip storage area can be assembled. In less than 24 hours, the entire system was erected – including roof installation.
The Plan Was Solid. Reality, However…
Naturally, we had a well-thought-out assembly plan. However:
“No plan survives first contact with reality.”
Our reality began with a heavy traffic jam around Hamburg. Four trucks delivering our materials were stuck – giving us time to wait and improvise.
At least the trucks arrived in the perfect sequence, allowing us to start assembling the heavy-duty steel containment basin immediately. Along the way, one of our favorite photos was taken – our technicians waiting in the morning sun. Almost iconic.
Thorough Preparation Means Faster Assembly
Thanks to our philosophy of fully assembling and testing every system at the factory prior to delivery, our technicians knew every single step inside out. Once the remaining trucks arrived, installation proceeded smoothly and efficiently.
By the end of the first day, the complete INOSTA was standing – even the sectional roof was already in place. The crane originally scheduled for day two was no longer needed at all.
Day Two: Fine-Tuning and Commissioning
The next morning, we took care of the final adjustments, thoroughly inspected the system – and were able to complete commissioning together with the client by around midday.
Our Conclusion:
A fantastic project, a strong team, and another prime example of how well-engineered technology, thorough preparation, and flexibility turn into genuine success stories.
Thank you to everyone involved for the excellent cooperation!